Iarnród Éireann and the NTA's multi-billion-euro electrification of Dublin's suburban rail across four sub-projects, plus the long-running history of the shelved DART Underground tunnel.
The DART+ Programme is the National Transport Authority and Iarnród Éireann's flagship rail-electrification capital programme for the Greater Dublin Area, planned to grow the electrified DART network from roughly 50 km to over 150 km across four sub-projects: DART+ West (Connolly/Spencer Dock to Maynooth and M3 Parkway, ~40 km, Railway Order granted by An Bord Pleanála on 18 July 2024 and operative from June 2025 after two judicial reviews were withdrawn); DART+ South West (Hazelhatch & Celbridge to Glasnevin via the Phoenix Park Tunnel, ~20 km, Railway Order granted on 13 November 2024); DART+ Coastal North (Malahide to Drogheda MacBride, ~37 km, Railway Order granted by An Coimisiún Pleanála on 25 August 2025); and DART+ Coastal South (still in preliminary design as of 2026). A separate fleet contract with Alstom for 285 X'trapolis carriages — €670 million across three orders — underpins the new services. Funding includes an €8.8 million EU Connecting Europe Facility grant for the Kildare-line studies (July 2020) and, under the July 2025 National Development Plan Review, a multi-billion allocation that pushed DART+ South West construction from 2026 to '2030+' with procurement in 2028–2029. Running behind the DART+ Programme is the long-running DART Underground / Interconnector proposal: scoped in the 2001 Platform for Change strategy, adopted under Transport 21 in 2005, granted a Railway Order by An Bord Pleanála in December 2011 weeks after Minister for Transport Leo Varadkar deferred funding in the November 2011 Infrastructure and Capital Investment 2012–2016 review, redesigned and then effectively cancelled by Minister Paschal Donohoe in September 2015, mothballed beyond 2042 in the NTA's 2022 Greater Dublin Area Transport Strategy, retained as DART+ Tunnel in the 2024 All-Island Strategic Rail Review, but not in any funded delivery pipeline.
National Transport Authority·Retrieved 2026-05-25high
Schedule
Target opening 2030
Delay risk 2–8 yr · DART+ West enabling works are signalled to start in late 2026, with first new Alstom DART+ trains entering service the same year. DART+ South West, despite consent secured in November 2024, has been pushed to '2030+' for construction by the 2025 NDP Review (procurement 2028–2029) — Trinity transport economist Brian Caulfield warned this delivery sequence risks 'fly[ing] in the face' of international best practice on enabling-infrastructure-first delivery. DART+ Coastal North construction is projected at roughly three years from detailed design. Aggregate programme delay risk is bounded on the low end by analogous overruns on Crossrail (~4 years) and on the high end by Irish judicial-review pattern around protected designations and capital re-prioritisation cycles.
DTO Platform for Change proposes the Interconnector tunnel
study
The Dublin Transportation Office's November 2001 strategy 'A Platform for Change — Outline of an integrated transportation strategy for the Greater Dublin Area 2000–2016' first formally proposed a heavy-rail Interconnector tunnel linking Heuston with the DART network via Pearse, St Stephen's Green and Spencer Dock. This is the originating document behind every subsequent DART Underground / DART+ Tunnel proposal.
Transport 21 adopts the DART Underground Interconnector
announcement
The Transport 21 capital programme, announced by Taoiseach Bertie Ahern and Minister for Transport Martin Cullen in November 2005 with a headline cost of €34 bn, formally adopted the DART Interconnector tunnel alongside Metro North as government policy. Delivery responsibility sat with the Railway Procurement Agency (later merged into Transport Infrastructure Ireland) and Iarnród Éireann.
Iarnród Éireann lodges DART Underground Railway Order with An Bord Pleanála
planning-decision
In June 2010 Iarnród Éireann submitted a Railway Order application under the Transport (Railway Infrastructure) Act 2001 for the 7.6 km DART Underground tunnel from Inchicore via Heuston, Christchurch, St Stephen's Green and Pearse to Docklands. The estimated cost was €4 bn, with anticipation of 2018 completion if construction began in 2012. An Bord Pleanála's oral hearing ran from late 2010 into 2011 and dealt with roughly 280 objections.
Minister Varadkar defers DART Underground in the 2012–2016 capital review
pause
On 10 November 2011 the Fine Gael–Labour government published its Infrastructure and Capital Investment Programme 2012–2016, deferring both DART Underground and Metro North. Transport Minister Leo Varadkar (who had confirmed the cancellation of the A5 Monaghan–Derry road project the day before) signed off on the capital cuts. Taoiseach Enda Kenny framed the choice as 'this is about choosing what the country needs most over the next few years and deferring other projects' until finances improved. Transport capital spending fell from €1.5 bn in 2011 to €0.8 bn by 2016.
An Bord Pleanála grants the DART Underground Railway Order — weeks after deferral
planning-decision
An Bord Pleanála granted the Railway Order for the 7.6 km DART Underground tunnel in December 2011, only weeks after the government had deferred its funding. The order authorised stations at Heuston, Christchurch, St Stephen's Green, Pearse and Docklands and stood as a live consent until 2025; the project never proceeded to construction.
Minister Donohoe ceases the €3 bn DART Underground in favour of redesign
cancellation
On the recommendation of the NTA, Minister for Transport Paschal Donohoe announced in September 2015 that the €3 bn DART Underground scheme as designed would be ceased and replaced with a 'lower-cost solution', with the Railway Order due to expire on 24 September 2015. The Irish Times reported on 8 September 2015 that Donohoe had briefed Cabinet colleagues the previous week. The 'lower-cost' DART+ programme — surface electrification of the Maynooth, Kildare and Northern lines — became the substitute.
EU Connecting Europe Facility grants €8.8 m for DART+ South West studies
other
On 20 July 2020 the European Commission announced a €8.8 million Connecting Europe Facility (CEF) grant to fund studies into the electrification, re-signalling, station upgrades and bridge replacements on the Kildare line — what would become DART+ South West. Senator James Lawless (Fianna Fáil, Kildare North) welcomed the funding as a 'next step' towards construction.
European Climate, Infrastructure and Environment Executive Agency (CINEA)·Retrieved 2026-05-25high
NTA publishes the €2.6 bn DART+ programme of surface electrification
announcement
On 26 August 2020 the National Transport Authority published the DART+ programme: surface electrification of three commuter lines (Northern, Maynooth/M3 Parkway, Kildare) to extend the DART beyond Dublin to Drogheda, Maynooth/M3 Parkway and Hazelhatch/Celbridge, plus an upgrade of the southern line to Greystones. The headline cost was €2 bn–€2.6 bn, with a fleet order of approximately 600 new carriages and elimination of multiple level crossings. The DART+ Tunnel question — successor to DART Underground — was explicitly excluded from the funded plan.
Draft GDA Transport Strategy 2022–2042 mothballs DART Underground beyond 2042
consultation
The NTA's draft Transport Strategy for the Greater Dublin Area 2022–2042 (published for public consultation on 9 November 2021) confirmed that the underground DART tunnel — successor to the 2011-approved scheme — would not proceed before 2042. NTA CEO Anne Graham stated the corridor would be 'preserved and protected' for delivery beyond the 20-year plan, citing modelling that the net public-transport ridership gain from the tunnel would be only ~10,000 per day on a 1.4 m/day base. The same strategy locked DART+ surface electrification into the 2022–2030 band.
National Transport Authority·Retrieved 2026-05-25high
Government grants Approval in Principle for DART+ West
announcement
In December 2021 the Government granted 'Approval in Principle' for the DART+ West element of the DART+ Programme, enabling Iarnród Éireann to proceed to a Railway Order application. The NTA Board had previously approved the DART+ Programme Preliminary Business Case for submission to the Department of Transport and Department of Public Expenditure and Reform; DART+ South West and DART+ Coastal elements remained subject to separate later approvals.
National Transport Authority·Retrieved 2026-05-25high
DART+ West Railway Order lodged with An Bord Pleanála
planning-decision
On Friday 29 July 2022 Iarnród Éireann lodged the DART+ West Railway Order application with An Bord Pleanála: 40 km of electrification from Maynooth and M3 Parkway to Connolly/Spencer Dock, twelve stations on the Maynooth line, three on the M3 Parkway line, a new Spencer Dock interchange station, six level-crossing closures and a new depot west of Maynooth. Minister for Transport Éamon Ryan welcomed the lodgement; NTA CEO Anne Graham and Iarnród Éireann CEO Jim Meade made supporting statements. The public consultation ran 5 August – 30 September 2022.
DART+ South West Railway Order lodged with An Bord Pleanála
planning-decision
On 22 March 2023 Iarnród Éireann lodged the Railway Order application for DART+ South West: 20 km of electrification, re-signalling and four-tracking from Hazelhatch & Celbridge via Park West / Cherry Orchard and the Phoenix Park Tunnel to Glasnevin, with capacity rising from 5,000 to 20,000 passengers per peak hour per direction. The application is An Bord Pleanála / An Coimisiún Pleanála case reference 316119.
DART+ Coastal North Railway Order lodged — DART extension to Drogheda
planning-decision
On 12 July 2024 the DART+ Coastal North Railway Order application was lodged with An Bord Pleanála: 37 km of electrification and re-signalling from Malahide to Drogheda MacBride, with platform reconfiguration at multiple stations and depot modifications to support new battery-electric trains. The application projects near-doubling of peak capacity from approximately 4,800 to 8,800 passengers per direction. Public consultation ran 19 July – 20 September 2024. Minister Éamon Ryan, NTA CEO Anne Graham and Iarnród Éireann CEO Jim Meade made statements.
An Bord Pleanála grants the DART+ West Railway Order
planning-decision
An Bord Pleanála granted the DART+ West Railway Order on 18 July 2024 (case reference 314232), authorising 40 km of electrification, a new Spencer Dock station with Luas Red Line interchange, and a second station entrance at Connolly via Preston Street. The Board attached a condition prohibiting construction of the proposed Maynooth-west depot due to flood-risk concerns, prompting Iarnród Éireann to pursue depot capacity separately under the DART+ Depot project.
An Bord Pleanála grants the DART+ South West Railway Order
planning-decision
An Bord Pleanála granted statutory approval for DART+ South West on 13 November 2024. The decision authorised electrification, re-signalling and four-tracking between Park West & Cherry Orchard and Heuston, plus services from Hazelhatch & Celbridge via the Phoenix Park Tunnel to Glasnevin. Iarnród Éireann CEO Jim Meade said: 'Today is a great day for the communities of North Kildare and South Dublin, the provision of DART services will transform commuting for the existing and new communities along this railway corridor.'
In November 2024 Iarnród Éireann unveiled the first five-carriage train of the new DART+ Fleet, built by Alstom under a framework agreement providing up to 750 electric and battery-electric carriages over a 10-year period. The rolling stock is the operational backbone of every DART+ infrastructure project: surface electrification is only useful once the new trains are in service.
Burke Brothers and Gowan Motor Group withdraw DART+ West judicial reviews
litigation
Two judicial-review challenges to the DART+ West Railway Order — by Burke Brothers (a hardware and electrical wholesale company near Ashtown) and the Gowan Motor Group — were withdrawn ahead of a three-day High Court hearing scheduled for 23 June 2025 before Mr Justice Garrett Simons. With the JRs gone the Railway Order became operative; Iarnród Éireann signalled enabling works could begin at the end of 2026, with the first of 185 new carriages entering service the same year. Cost was reported as 'around €1 billion'.
NDP Review 2025 reaffirms DART+ but slips DART+ South West to 2030+
statement
The July 2025 National Development Plan Review allocated multi-billion-euro funding to the DART+ Programme alongside MetroLink, BusConnects and the Western Rail Corridor — Minister for Transport Darragh O'Brien said the funding would 'enable us to progress' DART+ and BusConnects, framing the package against an NDP Sectoral Investment Plan for transport of 'over €10 billion'. However, the revised NDP schedule pushed DART+ South West construction from a previously expected 2026 start to '2030+' with procurement in 2028–2029, prompting criticism from transport economist Brian Caulfield (TCD) and Green Party transport spokesperson Feljin Jose, the latter saying the delay 'flies in the face' of policy on enabling housing infrastructure.
An Coimisiún Pleanála approves DART+ Coastal North
planning-decision
An Coimisiún Pleanála (the successor to An Bord Pleanála) approved the DART+ Coastal North Railway Order on 25 August 2025 — the third DART+ project to receive planning consent. The order authorises 37 km of electrification and re-signalling between Malahide and Drogheda MacBride, station reconfiguration at multiple locations and depot modifications. Iarnród Éireann CEO Jim Meade said the DART+ programme 'will truly revolutionise commuting in the Greater Dublin Area'. NTA Interim CEO Hugh Creegan described the decision as 'an important step in delivering a better-connected public transport for the region'. Case reference 320164. Construction projected to take roughly three years from detailed design completion, subject to funding.
Third Alstom carriage order brings DART+ fleet investment to €670 m
other
On 22 December 2025 the Department of Transport announced the third order from Alstom under the Iarnród Éireann framework — bringing total carriages ordered to 285 (57 five-carriage trains) at total fleet investment of €670 million. Minister for Transport Darragh O'Brien framed the order as part of the NDP Sectoral Investment Plan for transport that 'will see over €10 billion of investment in public transport infrastructure'. The new trains are required to actually run the services the DART+ infrastructure consents enable.
DART+ South West (Hazelhatch & Celbridge to Glasnevin via Phoenix Park Tunnel)
current20.0 km
Hazelhatch & Celbridge· terminus— Western terminus of DART+ South West; capacity rising from 5,000 to 20,000 passengers per peak hour per direction.
Park West & Cherry Orchard· junction— Start of approved four-tracking under DART+ South West.
Heuston West (proposed)· stationnot served— Mooted new station to serve Clancy Quay / Island Bridge; final inclusion subject to detailed design (status disputed in current project documentation).
Dublin Heuston· junction— Through-running enabled via the Phoenix Park Tunnel branch under DART+ South West.
Glasnevin (new interchange)· station— New interchange with the Maynooth and Northern lines; MetroLink also targets a station here.
The combined DART+ Programme is designed to double peak-hour rail capacity in the Greater Dublin Area from approximately 26,000 to 52,000 passengers per direction per hour, with proportionate gains on each sub-project: DART+ West rising from 5,000 to over 13,200; DART+ South West from 5,000 to 20,000; DART+ Coastal North from about 4,800 to 8,800. The intended modal shift away from car commuting is the core climate-policy rationale for the programme.
National Transport Authority·Retrieved 2026-05-25high
Decarbonisation of suburban rail and substitution for car kilometres
majorclimate
Replacing diesel commuter rolling stock with battery-electric / overhead-electric carriages on three of the four corridors out of Dublin removes a large fraction of the Iarnród Éireann fleet's tailpipe emissions, and the additional capacity is intended to support modal shift from private cars under the Climate Action Plan's 42–50% transport-emissions reduction target by 2030. The NTA's 2022 GDA Transport Strategy modelled DART+ as a core component of the package projected to deliver a 69% drop in transport emissions by 2042.
Multi-billion-euro exchequer exposure with rising central estimate
majorfiscal
DART+ South West alone was reported in the 2025 NDP Review at 'over €1 billion'; the overall DART+ Programme envelope is in the multi-billion-euro range when the four sub-projects, the €670 m Alstom fleet contract and depot works are aggregated, with funding sequenced over the NDP horizon to 2030 and beyond. The July 2025 NDP Review slipped DART+ South West construction from a 2026 start to '2030+' (procurement 2028–2029), raising real-cost-of-delay risk that compounds with construction-cost inflation.
National Transport Authority·Retrieved 2026-05-25high
Level-crossing closures and urban-realm interventions on DART+ West
moderatecommunity
DART+ West involves the closure of six level crossings along the Maynooth corridor (notably Ashtown Road, replaced with an underpass) and associated road-works on adjoining streets. Affected businesses including Burke Brothers (hardware/electrical wholesale) and the Gowan Motor Group brought judicial-review proceedings in the High Court over land-take and traffic-pattern effects on Mill Lane; both withdrew their challenges in June 2025 before the substantive hearing.
Through-running between south-west and north Dublin foregone — DART Underground unbuilt
majortransport-modal
By granting and then not funding the DART Underground Railway Order (2011), redesigning it (2015), and ultimately mothballing it beyond 2042 in the 2022 GDA Transport Strategy, the Irish state has effectively foregone the planned through-running of heavy rail between Heuston/Kildare and the Northern/Maynooth corridors via a city-centre tunnel — a structural constraint the NTA's own 2021 feasibility study acknowledged would need to be addressed 'over the longer term'. Critics of the 2022 strategy (including respondents to its public consultation) disputed the NTA's 10,000-net-new-passengers/day modelling, arguing the journey-quality benefit to tens of thousands of existing public-transport users was undervalued.
Member States must ensure that projects likely to have significant effects on the environment are subject to an environmental impact assessment before consent is granted; for rail infrastructure of the type included in DART+ this is a mandatory requirement of any Railway Order under the Transport (Railway Infrastructure) Act 2001.
If breached: Railway Order can be quashed on judicial review (the live risk that materialised with the Burke Brothers and Gowan Motor Group proceedings on DART+ West); CJEU infringement proceedings against the State.
Any plan or project not directly connected with the management of a Natura 2000 site, but likely to have a significant effect on it, must be subject to an 'appropriate assessment' of its implications for the site's conservation objectives. Relevant on DART+ Coastal North in particular given proximity to coastal SACs/SPAs north of Dublin.
If breached: Railway Order can be quashed on judicial review; project may only proceed under Imperative Reasons of Overriding Public Interest with compensatory measures (Art 6(4)).
Construction or operation of railway infrastructure of the kind included in DART+ requires a Railway Order made by An Bord Pleanála / An Coimisiún Pleanála under the 2001 Act, following statutory public consultation and (where relevant) an oral hearing. Compulsory Purchase Order powers attach.
If breached: No construction can lawfully proceed without the Order; the Order itself can be challenged by judicial review within statutory time limits.
Public bodies including the Department of Transport, NTA and Iarnród Éireann must perform their functions in a manner consistent with the State's climate objectives — net-zero by 2050 and a 51% cut in emissions by 2030 — and with sectoral emissions ceilings. DART+ is one of the largest single transport-decarbonisation interventions used to justify performance against the transport ceiling.
If breached: Judicial review of decisions inconsistent with the climate objectives; loss of headroom under the binding sectoral ceiling forces other parts of transport policy to compensate.
EU grant funding for trans-European transport network projects (including the €8.8 m CEF grant for DART+ South West/Kildare line studies in 2020) is conditional on compliance with the regulation's eligibility, monitoring and reporting requirements; sub-standard project delivery can trigger clawback.
If breached: Clawback of EU funds disbursed; ineligibility for future CEF calls.
DART+ is the central delivery vehicle, alongside MetroLink and BusConnects, for the rail commitments in the 2025 Programme for Government and the All-Island Strategic Rail Review the Government committed to act on.
Citizen objections(4)
Burke Brothers (hardware and electrical wholesale company)
litigation
Burke Brothers brought a judicial review of An Bord Pleanála's grant of the DART+ West Railway Order, arguing the project would 'significantly affect their operations' through land-take and changes to road layout near Ashtown station (including replacement of the Ashtown Road level crossing with an underpass and anticipated traffic increase on Mill Lane). The challenge was set down for a three-day hearing on 23 June 2025 before Mr Justice Garrett Simons but was withdrawn before the hearing.
Gowan Motor Group brought a separate judicial review of the DART+ West Railway Order alongside Burke Brothers, on broadly similar grounds — land-take and operational disruption from the Ashtown-area works. The challenge was also withdrawn ahead of the June 2025 hearing.
Following publication of the NDP Review that pushed DART+ South West construction to 2030+, Green Party transport spokesperson Feljin Jose argued the delay decisions 'fly in the face' of government policy on enabling infrastructure to unlock housing, attributing them to reduced public-transport funding allocations within the revised plan.
Pro-DART-Underground respondents to the 2021 GDA Strategy public consultation
public consultation
Multiple respondents to the NTA's draft Transport Strategy for the GDA 2022–2042 disputed the modelling underpinning the decision to defer DART+ Tunnel beyond 2042 — specifically the NTA's claim that the tunnel would attract only ~10,000 net new public-transport users per day. Respondents argued the journey-quality and reliability benefit to existing public-transport users was undervalued and that the project should not be deferred. The NTA's Public Consultation Report records the dispute but the deferral position was retained.
The other half of Dublin's 'great unbuilt' heavy-rail project: scoped in the same 2001 Platform for Change strategy, granted a 2011 Railway Order (as Metro North) shelved weeks later in the same November 2011 capital cuts, re-launched 2015 / re-branded MetroLink 2018, finally granted a Railway Order on 2 October 2025. The pattern — long planning, intermittent political will, repeated re-scoping — is the closest domestic analog for the DART Underground story.
Approved late 2007 at £15.9 bn for opening December 2018; delivered in stages from May 2022 (~4 years late) at approximately £18.9 bn (~£3 bn / ~€4 bn over baseline). UK National Audit Office and Public Accounts Committee identified systems-integration underestimation as the principal failure mode — directly analogous to the systems-integration phase the DART+ programme enters post-Railway-Order.
UK Parliament (Public Accounts Committee)·Retrieved 2026-05-25high
Navan Rail Line
0.0 yr delay
Sister project under the All-Island Strategic Rail Review and 2022 GDA Transport Strategy. The Navan EPR (published 20 May 2026) is the most recent re-announcement on the Dublin commuter rail family; the relationship of DART+ to Navan Rail is that DART+ West's electrification to M3 Parkway is the natural Dublin-end interface for any future Navan extension.